Skip to Content.
Sympa Menu

building-1150-2m-floor-outages - [building-1150-2m-floor-outages] *ALERT* Health System Planned Outage - Hospital 2M Floor Affected

Subject: Building 1150 2M Floor outages

List archive

[building-1150-2m-floor-outages] *ALERT* Health System Planned Outage - Hospital 2M Floor Affected


Chronological Thread  
  • From: UVA Facilities Management <>
  • To:
  • Subject: [building-1150-2m-floor-outages] *ALERT* Health System Planned Outage - Hospital 2M Floor Affected
  • Date: Tue, 6 Dec 2022 08:41:23 -0500 (EST)
  • Authentication-results: eifmailue2p2.az.virginia.edu; spf=pass (virginia.edu: domain of designates 52.203.46.154 as permitted sender) ;

 

*ALERT*ALERT*ALERT*ALERT*

Health System Planned Outage Notification

Please Post Centrally in Your Department



HVAC Outage    
   
AHU-2MA-1 & Standby AHU-2M-West

 

BLDG: 1150 University Hospital
AFFECTED FLOORS:
  Ground 2M
Central Sterile Wash & Clean Storage


   

Tying in Standby AHU-2M-West supply air to AHU-2MA-1 distribution supply air ducts so demolition of AHU-2MA-1 replacement can begin.

***Please Review Your Local Downtime Activation Plan in Advance of This Outage***

While no interruptions in service are expected, beyond those indicated in this notice, you should review your local area response plan prior to the outage.  For unexpected issues related to this outage please report to Help Desk at 4-2267 and your local clinical leadership for operational response.


Scheduled Start Date and Time: 2022-Dec-18 07:00
Scheduled End Date and Time: 2022-Dec-18 11:00
Work Order Number: 3107699-93700
  Outage Number:  2

Outage Coordinator: Scott Guynes 434-282-3794
  POC for Group Performing Work:

  Colonial Webb  Tony Casey 4348250456
Customers with Whom the Outage was Coordinated:

Kevin Elgin - Director - CSS
Kevin Henderson - Supervisor - HSPP Zone 1 South HVAC
Mike Rose - Shift Supervisor - HSPP Zone 1 South
Alex Harlow - Supervisor - F&LS


The specified utility or utilities will be out of service as noted.  Please advise the Outage Coordinator immediately if this cannot be accommodated in areas under your control or direction.

*ALERT*ALERT*ALERT*ALERT*
Please use the below link to unsubscribe from these notification, change, or subscribe to other building lists
 

Attachment: 13269 Planned Outage HVAC 1150 University Hospital.pdf
Description: Adobe PDF document




Archive powered by MHonArc 2.6.24.

Top of Page