Skip to Content.
Sympa Menu

building-1150-2m-floor-outages - [building-1150-2m-floor-outages] ***ALERT*** Health System Planned Outage Affecting Hospital 2M Floor - EXTENDED

Subject: Building 1150 2M Floor outages

List archive

[building-1150-2m-floor-outages] ***ALERT*** Health System Planned Outage Affecting Hospital 2M Floor - EXTENDED


Chronological Thread 
  • From: UVA Facilities Management <>
  • To:
  • Subject: [building-1150-2m-floor-outages] ***ALERT*** Health System Planned Outage Affecting Hospital 2M Floor - EXTENDED
  • Date: Fri, 9 Aug 2019 09:38:25 -0400 (EDT)
  • Authentication-results: eifmailuw2p2.az.virginia.edu; spf=pass (virginia.edu: domain of designates 52.203.46.154 as permitted sender)

 

*ALERT*ALERT*ALERT*ALERT*  

Health System Planned Outage 

Please Post Centrally In Your Department

 HVAC  Outage -  EXTENDED  
 

BLDG: 1150 University Hospital

AFFECTED FLOORS:  
    Second       2M 
UHE Floors 2 & 2M

 

Need to shut down all HVAC serving floors 2 & 2M in the new Hospital Expansion (ONLY) for a week to install new ductwork & Fire / Smoke Dampers in the main sections of ductwork for these floors. There currently isn't any hospital staff moved in on these floors, but sending notice for those who are preparing to move in.

Extended Scheduled End Date and Time: 2019-Aug-19 07:00  


Outage Number: 142


Work Order Number: 2494485


Outage Coordinator: Scott Guynes   434-282-3794


POC for Group Performing Work

Skanska  Rick Chandler 813-376-8139


The specified utility or utilities will be out of service as noted. Please advise the Outage Coordinator immediately if this cannot be accommodated in areas under your control or direction.

*ALERT*ALERT*ALERT*ALERT*

Please use the below link to unsubscribe from these notification, change, or subscribe to other building lists
 

Attachment: printview.pdf
Description: Adobe PDF document