Subject: Building 0253 University Press Warehouse outages

List archive

[building-0253-outages] *ALERT* *ALERT* Facilities Management Chilled Water Outage Notice - UNIVERSITY PRESS WAREHOUSE 2021-Mar-04 07:30 AM


Chronological Thread 
  • From: UVA Facilities Management <>
  • To:
  • Subject: [building-0253-outages] *ALERT* *ALERT* Facilities Management Chilled Water Outage Notice - UNIVERSITY PRESS WAREHOUSE 2021-Mar-04 07:30 AM
  • Date: Thu, 25 Feb 2021 15:20:51 -0500 (EST)
  • Authentication-results: eifmailue2p2.az.virginia.edu; spf=pass (virginia.edu: domain of designates 52.37.219.182 as permitted sender)

 

    

9290

    *ALERT*ALERT*ALERT*ALERT*

Facilities Management Outage Notification

Please Post Centrally in Your Department

 

Chilled Water Outage    


BLDG: 0253 UNIVERSITY PRESS WAREHOUSE
 
ALL FLOORS AFFECTED  

Impact to Building Occupants:  No Cooling
The outage is scheduled for 2 days but will try to complete in 1 day.





Scheduled Start Date and Time:

2021-Mar-04 07:30 AM
Scheduled End Date and Time:

2021-Mar-05 03:00 PM
Reason for Outage:  
Tie in new chilled water lines for HVAC system. Will also need welding done on this day.

Requested By: 
Bret Gentry (UVA FM Project Services)

Outage Coordinator  
Bret Gentry  434-531-8211  
  
Customers with Whom the Outage was Coordinated:  
 
June Bates

Outage Approved By:
Kenny Bower (UVA - Facilities Management)


Important Notes:
  1. The specified utility or building system will be out of service as noted above.  Please advise the Outage Coordinator immediately if this can not be accommodated in areas under your control or direction
  2. Those performing work associated with this outage MUST  notify the Systems Control Center (982-4685) PRIOR TO THE START and upon COMPLETION of all work

*ALERT*ALERT*ALERT*ALERT*

Please use the below link to unsubscribe from these notification, change, or subscribe to other building lists
 

Attachment: Assistance Requested: Energy & Utilities Planned Outage UNIVERSITY PRESS WAREHOUSE.pdf
Description: Adobe PDF document



  • [building-0253-outages] *ALERT* *ALERT* Facilities Management Chilled Water Outage Notice - UNIVERSITY PRESS WAREHOUSE 2021-Mar-04 07:30 AM, UVA Facilities Management, 02/25/2021

Archive powered by MHonArc 2.6.24.

Top of Page