  • Subject: [building-0067-outages] *ALERT* *ALERT* Facilities Management Chilled Water Outage Notice - Halsey Hall 2025-Oct-03 06:00
  • Date: Tue, 30 Sep 2025 14:32:14 -0400 (EDT)

 

University of Virginia Logo

    

25472

    *ALERT*ALERT*ALERT*ALERT*

Facilities Management Outage Notification

Please Post Centrally in Your Department

 

Chilled Water Outage    


BLDG: 0067 Halsey Hall
 
ALL FLOORS AFFECTED  

Impact to Building Occupants:  No Cooling No Heating
We will get heating and cooling back online ASAP. The system will still be able to circulate fresh air into the building, but no cooling would be applied.

Please email our team to confirm the outage at:
Randy Spencer –
Jacob Campbell –





Scheduled Start Date and Time:

2025-Oct-03 06:00
Scheduled End Date and Time:

2025-Oct-03 14:00
Reason for Outage:   
Replace chilled water and heating water bad valves. 8 total. 2 loops chilled, 2 loops heating.

Requested By:  
Logan Kendle

Outage Coordinator   
Donald (Randy) Spencer  434-531-6993 
  
Customers with Whom the Outage was Coordinated:  
 
Erin Printy
Wayne Bourne

Outage Approved By:
Randy Spencer (UVA FM Operations)


Important Notes:
  1. The specified utility or building system will be out of service as noted above.  Please advise the Outage Coordinator immediately if this can not be accommodated in areas under your control or direction
  2. Those performing work associated with this outage MUST  notify the Systems Control Center (982-4685) PRIOR TO THE START and upon COMPLETION of all work

*ALERT*ALERT*ALERT*ALERT*

Please use the below link to unsubscribe from these notification, change, or subscribe to other building lists

This email was sent on behalf of University of Virginia by Veoci
© 2025 Veoci Inc.
 

Attachment: pdfqpcg_Z993K.pdf
Description: Adobe PDF document



  • [building-0067-outages] *ALERT* *ALERT* Facilities Management Chilled Water Outage Notice - Halsey Hall 2025-Oct-03 06:00, UVA Facilities Management, 09/30/2025

Archive powered by MHonArc 2.6.24.

Top of Page