23660

    *ALERT*ALERT*ALERT*ALERT*

Facilities Management Outage Notification

Please Post Centrally in Your Department

 

Fire System Fire Suppression,Fire System Panel,Smoke Detection,Sprinkler System Outage    


BLDG: 0058 Rouss Hall
 
Affected Floors / Rooms:  3rd and 2nd floors

Impact to Building Occupants:  No Fire Alarms No Fire Suppression
Fire Sprinkler System will be taken offline while the sprinkler heads are turned up in preparation for drop ceiling demo.

Please Confirm you have received notification of this outage by emailing our Team at:
Randy Spencer:
Jacob Campbell:





Scheduled Start Date and Time:

2025-May-21 07:00
Scheduled End Date and Time:

2025-May-21 16:00
Reason for Outage:   
Turning up sprinkler heads as the drop ceiling is removed.

Requested By:  
Brandon Adams

Outage Coordinator   
Donald (Randy) Spencer  434-531-6993 
  
POC for Group Performing Work:
Virginia Sprinkler Company  Chris Leavitt 804-459-2200    

FM Responsible Person:  Brandon Adams  434-987-7005
Customers with Whom the Outage was Coordinated:  
 
Bryan Lewis

Outage Approved By:
Randy Spencer (UVA FM Operations)


Important Notes:
  1. The specified utility or building system will be out of service as noted above.  Please advise the Outage Coordinator immediately if this can not be accommodated in areas under your control or direction
  2. Those performing work associated with this outage MUST  notify the Systems Control Center (982-4685) PRIOR TO THE START and upon COMPLETION of all work

*ALERT*ALERT*ALERT*ALERT*

Please use the below link to unsubscribe from these notification, change, or subscribe to other building lists

This email was sent on behalf of University of Virginia by Veoci
© 2025 Veoci Inc.
 

Attachment: Assistance Requested: Planned Outage Rouss Hall Fire System.pdf
Description: Adobe PDF document



  • [building-0058-outages] *ALERT* *ALERT* Facilities Management Fire System Fire Suppression,Fire System Panel,Smoke Detection,Sprinkler System Outage Notice - Rouss Hall 2025-May-21 07:00, UVA Facilities Management, 05/14/2025

Archive powered by MHonArc 2.6.24.

Top of Page